Preparing To Capture

This topic outlines the tasks you should complete before you initiate the capture of your source server.

Verifying the Source Server Configuration

Before you migrate a source server, ensure that the server meets the criteria outlined in this topic.

Source Server Minimum RAM Requirement

The source server must have at least 1GB of available RAM.

Source Server System Time

Some operations between DynaCenter and the DynaCenter agent are time stamp sensitive. The time on the source server must be set correctly before you can migrate the server.

 